problem with a revised expression

count(if(aggr(only(dateQA - dateCT), Pat_ID1) <= (LengthDays*7/5),1))

Hi all

the above expression works but ...

I want to improve it!

a.     using NetWorkDays(dateQA,dateCT) instead of (dateQA - dateCT)  This could be giving me a problem because it is giving a "fraction" of a date?? ...

LengthDays*7/5 was an attempt to allow for weekends but with NetWorkDays - the 7/5 compromise will not be needed.

but I then I start getting errors ...

So what I am trying to say is:

a particular Pat_ID1 has x number of days between dateQA and date CT

if this x number of days is less than or equal to a specified LengthDays then give them a count of 1.

Jo

4 Replies
settu_periasamy
Master III
Master III

Have you tried with 'floor' function?

like

Networkdays(floor(dateQA),floor(dateCT))

josephinetedesc
Creator III
Creator III
Author

I found out what I have been doing wrong! 

The difference in the first and second image is that the second image had as an expression '1'  - this was because I wanted all rows to show.

However I could solve the problem (without the expression "1") - by ensuring that the "Suppress zero-values" was unchecked!  I now need to check how negative values are shown.

Capture1.JPG

josephinetedesc
Creator III
Creator III
Author

If the difference between 2 dates is negative -the function NetWorkDays() gives 0 .. How am I able to keep the 0 value in rowNum3, but not the 0 in rowNum6?

Capture1.JPG

settu_periasamy
Master III
Master III

Hi,

Have you got resolved?, if not, try like this..

=if(dateCT<dateQA,

     NetWorkDays(dateCT,dateQA),

     NetWorkDays(dateQA,dateCT))