Hi All,

I have 5 tasks which are depending on each other. In order to stop the tasks execution, is it ok if i disable only the first task? OR Do i need to disable all tasks manually. By the way all the tasks are depending on each other.

Like:

Task1

     Task2

            Task3

                    Task4

Here the task2 will execute only on the  successful execution of Task1. Similarly for other tasks have dependency.

Thank you.

Regards,

Viresh

1 Solution

Accepted Solutions
rahulpawarb
Specialist III
Specialist III

You can disable the first task; this will do the trick; if someone triggers the intermediate task then subsequent tasks will be started. So disabling all the tasks will help you to avoid unnecessary execution of other tasks.

Hope this will help,

Regards!

Rahul Pawar

View solution in original post

2 Replies
Muthu
Partner - Creator III
Partner - Creator III

Disabling only task1 would be fine.

rahulpawarb
Specialist III
Specialist III

You can disable the first task; this will do the trick; if someone triggers the intermediate task then subsequent tasks will be started. So disabling all the tasks will help you to avoid unnecessary execution of other tasks.

Hope this will help,

Regards!

Rahul Pawar