Hi,
There is a job with reload and distribution task. Even when the reload is failing after reloading for few hours and is getting distributed with the partial reload of the data?
Is there any way to avoid the distribution task to run until the reload task has been successfully completed?
Thanks
Yes. By creating dependancings in the Job (8.5 Publisher) you can have the distribution dependent on a completion of the reload when you add the tasks into the job.
In v9 when you create the task trigger on the source document you can configure the trigger to start the task on the event from another task. This can be either a successful or failed completion of another task. In your case you would want on successful completion of reload task.