how to do independent job scheduling?
Hi Venu,
Independent job scheduling means what.
we have so many ways to schedule the jobs.we can schedule the job directly in server or we can create a batch file and schedule that job in task schduler
In the task->trigger->we can schedule the job.
It will act as individual task with out dependency.
Hi,
You need to schedule it via .Bat file.
Basic syntax is:-
"c:\Program Files\QlikView\QV.exe" /r c:\ApplicaitonFolderName\Application.qvw
Steps:-
1. Open notepad and write code
"c:\Program Files\QlikView\QV.exe" /r c:\ApplicaitonFolderName\Application.qvw
2. And then save it with the Filename.bat in any location
Ex:- Reload.Bat
3. Double click on the Bat file you are able to reload the application.
4. You can even use windows task scheduler to triggered the bat file.
Regards