Challenge:
- Show, in a pivot table, for each date in, the accumulated planning for the coming 5 days
- Show maximum 5 dates starting the last date in the selection
For example, if sep 22nd is selected, for each date, show the accumulated planning for the coming 5 days = (DateX) + (DateX+1) + (DateX+2)+ (DateX+3)+ (DateX+4)
=If(RefDate <= '$(vceMaxDate)' and RefDate >= '$(vceMinDate)',RefDate)
Whereas :
RefDate field - Date from date island (not connected to the rest of the data model)
vceMinDate variable - should be the last date on selection = Max(Date)
vceMaxDate variable = vceMinDate + 4
Challenge1: calculated dimmension does not allow aggregation
Sum(If(Date >= aggr(NODISTINCT max(RefDate),MachineId,RefDate) and
Date <= Date(aggr(NODISTINCT max(RefDate),MachineId,RefDate)+4),planning)
This will not work when a single date is selected. Qlikview will, then, only show the planning for that single day.
This calls for Set Analysis but as far as i know, it calculates one time per object
Challenge2: use set analysis to accumulate planning but disregarding date selection
I've attached an example.
appericiate your help,
Dror
Challenge:
- Show in a pivot table, for each date in the selected week, the accumulated planning for the coming 5 days
- For example, if sep 22nd is selected, for each passing 5 days, show the accumulated planning for the coming 5 days = (DateX) + (DateX+1) + (DateX+2)+ (DateX+3)+ (DateX+4)k
Hi drorsvr,
maybe like attached?
I just added a set identifier {1} to your table expression. And set your vceminDate Variable to =max(Date) (I think your calendar input box is somehow contra productive here).
So if I select a Date from the list box a the right, I should get the correct planning for following 5 days.
regards,
Stefan
Hi drorsvr,
maybe like attached?
I just added a set identifier {1} to your table expression. And set your vceminDate Variable to =max(Date) (I think your calendar input box is somehow contra productive here).
So if I select a Date from the list box a the right, I should get the correct planning for following 5 days.
regards,
Stefan