Date according Business Days

Hello Everyone,

Need your help to find out Start date:

Table:

OrderLinePartsCleanedDatePlanDateOutputDate
571201578701088/7/20207/22/2020 
571201578701088/7/20207/23/2020 
571201578701088/7/20207/24/2020 
571201578701088/7/20208/3/2020 
571201578701088/7/20208/4/2020 
57120157P118888/7/20207/29/2020 
57120157P118888/7/20207/30/2020 
57120157P118888/7/20207/31/2020 
CWET1579797978/3/20208/5/20208/5/2020
CWET1579797978/3/20208/9/20208/9/2020
CWET1579797978/3/20208/10/20208/10/2020
CWET157YTR7898/4/20208/5/20208/9/2020
CWET157YTR7898/4/20208/9/20208/9/2020
CWET157YTR7898/4/20208/12/20208/12/2020

 

Here in my raw data - there are two date fields (CleanedDate and PlanDate). I Need output field with given below scenorios.

1.Need to check PlanDate to CleanedDate + 2 Business days (function - Networkdays (Monday to Friday)) ,

In below case

OrderLinePartsCleanedDatePlanDateOutputDate
571201578701088/7/20207/22/2020 
571201578701088/7/20207/23/2020 
571201578701088/7/20207/24/2020 
571201578701088/7/20208/3/2020 
571201578701088/7/20208/4/2020 

CleanedDate+2BD = 8/9/2020 and PlanDate Started From 7/22/2020 to 8/4/2020, In this case CleanedDate not present in PlanDate, hence this data should be blank.

2. Need to check PlanDate to CleanedDate + 2 Business days (function - Networkdays (Monday to Friday)) ,

In below case

CleanedDate+2BD = 8/6/2020 and PlanDate Started from 8/5/2020. In this case the PlanDate should be equal to 8/6/2020 or whatever greater is present in PlanDate.

OrderLinePartsCleanedDatePlanDateOutputDate
CWET157YTR7898/4/20208/5/2020 
CWET157YTR7898/4/20208/9/20208/9/2020
CWET157YTR7898/4/20208/12/20208/12/2020

 

Thanks in advance for your input.

Labels (2)
1 Solution

Accepted Solutions
Taoufiq_Zarra
MVP
MVP

@rakeshkumar1890  May be like this

load *,if(LastWorkDate(CleanedDate+1, 2)<PlanDate,PlanDate) as OutputDate;

LOAD OrderLine, Parts, Date#(CleanedDate,'M/D/YYYY') as CleanedDate, Date#(PlanDate,'M/D/YYYY') as PlanDate  INLINE [
    OrderLine, Parts, CleanedDate, PlanDate
    57120157, 870108, 8/7/2020, 7/22/2020
    57120157, 870108, 8/7/2020, 7/23/2020
    57120157, 870108, 8/7/2020, 7/24/2020
    57120157, 870108, 8/7/2020, 8/3/2020
    57120157, 870108, 8/7/2020, 8/4/2020
    57120157, P11888, 8/7/2020, 7/29/2020
    57120157, P11888, 8/7/2020, 7/30/2020
    57120157, P11888, 8/7/2020, 7/31/2020
    CWET157, 979797, 8/3/2020, 8/5/2020
    CWET157, 979797, 8/3/2020, 8/9/2020
    CWET157, 979797, 8/3/2020, 8/10/2020
    CWET157, YTR789, 8/4/2020, 8/5/2020
    CWET157, YTR789, 8/4/2020, 8/9/2020
    CWET157, YTR789, 8/4/2020, 8/12/2020
];

 

output:

Capture.PNG

 

8/7/2020+2BD is 11 not 9 ?

Regards,
Taoufiq ZARRA

"Please LIKE posts and "Accept as Solution" if the provided solution is helpful "

(you can mark up to 3 "solutions") 😉

View solution in original post

2 Replies
Taoufiq_Zarra
MVP
MVP

@rakeshkumar1890  May be like this

load *,if(LastWorkDate(CleanedDate+1, 2)<PlanDate,PlanDate) as OutputDate;

LOAD OrderLine, Parts, Date#(CleanedDate,'M/D/YYYY') as CleanedDate, Date#(PlanDate,'M/D/YYYY') as PlanDate  INLINE [
    OrderLine, Parts, CleanedDate, PlanDate
    57120157, 870108, 8/7/2020, 7/22/2020
    57120157, 870108, 8/7/2020, 7/23/2020
    57120157, 870108, 8/7/2020, 7/24/2020
    57120157, 870108, 8/7/2020, 8/3/2020
    57120157, 870108, 8/7/2020, 8/4/2020
    57120157, P11888, 8/7/2020, 7/29/2020
    57120157, P11888, 8/7/2020, 7/30/2020
    57120157, P11888, 8/7/2020, 7/31/2020
    CWET157, 979797, 8/3/2020, 8/5/2020
    CWET157, 979797, 8/3/2020, 8/9/2020
    CWET157, 979797, 8/3/2020, 8/10/2020
    CWET157, YTR789, 8/4/2020, 8/5/2020
    CWET157, YTR789, 8/4/2020, 8/9/2020
    CWET157, YTR789, 8/4/2020, 8/12/2020
];

 

output:

Capture.PNG

 

8/7/2020+2BD is 11 not 9 ?

Regards,
Taoufiq ZARRA

"Please LIKE posts and "Accept as Solution" if the provided solution is helpful "

(you can mark up to 3 "solutions") 😉
rakeshkumar1890
Creator
Creator
Author

Big thanks Taoufiq