On multiple triggers - Third trigger doesn't work

Hi

We are using SR7.

It seems like when using On multiple triggers with 3 triggers, the dependent task starts after just 2 triggers finished, while the third is still running.

Is there a known bug? and if so, what version will fix this?

I'm using SR5 in another project, where this  issue seems to be fine..

Thanks

Labels (1)