how do i do a waterfall chart that project info are on y axis, and time is on x axis, and the length of bar is the duration of the project. i made one using end_date-start_date, but the chart is plotted in # of days, not the dates, 2011-01-01 on x axis.

help please

Labels (1)
1 Reply
Gysbert_Wassenaar
Partner - Champion III
Partner - Champion III

I think this blog post may help you. It explains using the bar offset setting.