How does execution plan works in talend integration cloud

Hi,

 

I haven't tried execution plan ever in TIC. I would like to know, if I add 5 tasks in execution plan, will they execute parallelly  or one after another? 

 

 

Thanks,

Suneel.

Labels (2)
5 Replies
manodwhb
Champion II
Champion II

@Suneel,yes you can execute parallel of 5 tasks,

check the below link for more details.

https://help.talend.com/reader/APEizOO00cdqC32~d2IJxA/7jtTN2JXAMzjapLjwbxeaA

Anonymous
Not applicable
Author

Hi,

 

    Since you are using Talend Cloud, you will have to refer the below help guide.

 

https://help.talend.com/reader/4ghjK9KsJCzsAAqMsfGL3g/7695z7iI45N4cldHpNL~_A

 

     You can schedule multiple jobs in parallel in Talend Cloud also. But you will have to decide whether you need to wait for all tasks to be completed to go to next stage or whether one task completion is fine to go to next stage.

0683p000009M16u.png

 

I hope this details helps to resolve your query. 

 

 

Warm Regards,

 

Nikhil Thampi

Anonymous
Not applicable
Author

Hi,
 
Do one step is one stage?
There is a requirement like 5 tasks need to be run one after another. So, Do I need to create each step with each task in it. Can u suggest me?
 
Thanks,
Suneel
manodwhb
Champion II
Champion II

@Suneel,in plan you can add all the 5 tasks,please check below.

 

0683p000009M1LD.png

Anonymous
Not applicable
Author

I want jobs to be run sequentially, not parallelly. Yes, they execute one after another when I add them in steps.
I just wanted to know will it be possible like they run independent of each other. I mean even if one job got failed it has to execute the following job.

Is this possible?