Hi Team,
I have a Main Job and a Sub-Job (with trunjob). I need to run the Main Job by schedule.
So, I created Build Job from the Main Job, then running the .bat from Task Scheduler.
My question is, should I created also for Sub-Job? or just only Main Job and its will works for whole Job (Main Job and Sub-Job) ?
Regards.
@Ilham Raspati , if you build main job that will take it up subjobs as well and it will create single package. no need to build subjobs separately.
Thanks,
Manohar
@Ilham Raspati , if you build main job that will take it up subjobs as well and it will create single package. no need to build subjobs separately.
Thanks,
Manohar
Just export the bat file of main job and schedule it to run, it will work for the whole job.
@Manohar B and @Shicong Hong ,
understood! Thank you for the explanation.
Thank's