HI All ,

I am searching for a solution to replicate Burnup(Planned vs Completed ) and Burndown (Planned VS Remaining)chart based on the attached data . The Output I am expecting is as follows:

d_ankusha_0-1682321433492.png

d_ankusha_2-1682321468823.png

 

 

I tried using RangeSum() and Modifier(Accumulation ) in the front end but the desired output is not generated.

 

Thanks for the help. @sunny_talwar @marcus_sommer @Patric_Nordstrom 

Qlik Sense Business  

 

Labels (6)
1 Reply
vikasmahajan

you can refer this :

https://community.qlik.com/t5/App-Development/Burn-down-chart/td-p/1404470

 

attached solution:

 

Hope this resolve your issue.
If the issue is solved please mark the answer with Accept as Solution & like it.