Hi All, 

I wanted to understand the below script in master calendar  speciall what is   "IterNo() -1 <= Today()" works (what is -1) ?

AutoGenerate 1 While $(varMinDate) + IterNo() -1 <= Today()

 

Thanks in Advance

Labels (5)
1 Solution

Accepted Solutions
Or
MVP
MVP

The first iteration is iteration #1, so one is typically subtracted to start at 0 (which would be whatever value is in varMinDate), rather than starting at varMinDate + 1.

View solution in original post

1 Reply
Or
MVP
MVP