Dear Sir

Can someone advise me why Jan 1, 2024 is missing after loading data from Excel.xlsx and why 'Monday' in all months are also missing ?.

Wishing you and your family a Happy New Year 2014!

Date Cdate
01-01-2024  
02-01-2024  
03-01-2024  
04-01-2024  
05-01-2024  
06-01-2024  
07-01-2024  
08-01-2024  
09-01-2024  
10-01-2024  
11-01-2024  
12-01-2024  
13-01-2024  
14-01-2024  
15-01-2024  
16-01-2024  

Many Thanks, Tracy

 

Labels (1)
1 Solution

Accepted Solutions
anat
Master
Master

as in table you can uncheck "Suppress zero-Values " option then you can see Monday as well 1/1/2024 records...

anat_0-1704087780738.png

 

but ideally it should not happen,,

anat_1-1704087895750.png

 

View solution in original post

2 Replies
anat
Master
Master

as in table you can uncheck "Suppress zero-Values " option then you can see Monday as well 1/1/2024 records...

anat_0-1704087780738.png

 

but ideally it should not happen,,

anat_1-1704087895750.png

 

anat
Master
Master

Or else you can generate day, month, week name etc... In load script like

Load day(date) as day, 

Week name(date) as week name