Question:

When I link a task/trigger to a 2nd task.  Does the second task still need a trigger?   

Labels (1)
1 Solution

Accepted Solutions
AJ_Ruggiero
Former Employee
Former Employee

The second task does not need a trigger. Once the first task is completed, then the second task will begin. 

View solution in original post

2 Replies
AJ_Ruggiero
Former Employee
Former Employee

The second task does not need a trigger. Once the first task is completed, then the second task will begin. 