      Hi Guys,

       

      is there any issue with rolling 6 weeks logic of mine. it works fine sometimes and sometimes does not work

       

      ='("' & concat({<MonthAndYearID={">=$(vprevweek)<=$(curweek)"}>} distinct WeekAndYear,'"|"') & '")'


      $(vprevweek)=max(MonthAndYearID)-20
      $(curweek)=max(MonthAndYearID)-17

       