HI guys,
is it possible and how to do in Data Load Editor, that the last two years only are loaded ?
i.e. this first line, to be something like DATE where Date= today(year) - 1 (or -2) not sure what would be the solution
LOAD
Date(Date#([Run_Date], 'YYYYMMDD') ) AS [Run_Date],
[Division],
[Company_Code],
[Material_Number],
[Material_Description],
[HFI_Quantity],
[Stock_Value],
[Currency]
FROM Table.Example
(txt, unicode, embedded labels, delimiter is '|', msq);
THANK YOU IN ADVANCE
ENA
LOAD
Date(Date#([Run_Date], 'YYYYMMDD') AS [Run_Date],
[Division],
[Company_Code],
[Material_Number],
[Material_Description],
[HFI_Quantity],
[Stock_Value],
[Currency]
FROM Table.Example
(txt, unicode, embedded labels, delimiter is '|', msq)
Where Date(Date#([Run_Date], 'YYYYMMDD') )>=yearstart(today(),-1);
If it's supposed to be a two years period, then maybe:
Where Date#(Run_Date,'YYYYMMDD') > AddYears(Today(),-2)