Hello Everyone!

I am trying to make a strigh forward forecast chart, and I have been googling and I found someone talking about creating a master calender and how to perform a simple linger regression; however, I am stuck at, what I believe is, a weird error. Please find below my script and the error associated with it:

QuartersMap: 

MAPPING LOAD  

rowno() as Month, 

'Q' & Ceil (rowno()/3) as Quarter 

AUTOGENERATE (12); 

Temp: 

Load 

               Date(min(MYDATEFIELD)) as minDate,  //Enter YourDateField from your data table

               Date(max(MYDATEFIELD)+90) as maxDate  //Generate dates until 3 months from max date for regression

Resident MYTABLE; 

Let varMinDate = Num(Peek('minDate', 0, 'Temp')); 

Let varMaxDate = Num(Peek('maxDate', 0, 'Temp')); 

DROP Table Temp; 

 

TempCalendar: 

LOAD 

               $(varMinDate) + (IterNo()-1) As Num, 

               Date($(varMinDate) + IterNo() - 1) as TempDate 

               AutoGenerate 500; //1 While $(varMinDate) + IterNo() -1 <= $(varMaxDate);  (this was giving an error until I changed it to 500)

 

MasterCalendar: 

Load 

               TempDate AS MYDATEFIELD,  //This field is the key that connects to the data table

               week(TempDate) As Week, 

               Year(TempDate) As Year, 

               Month(TempDate) As Month, 

               Day(TempDate) As Day, 

               YeartoDate(TempDate)*-1 as CurYTDFlag, 

               YeartoDate(TempDate,-1)*-1 as LastYTDFlag, 

               inyear(TempDate, Monthstart($(varMaxDate)),-1) as RC12, 

               date(monthstart(TempDate), 'MMM-YYYY') as MonthYear,  //This will be your dimension in the line-chart

               ApplyMap('QuartersMap', month(TempDate), Null()) as Quarter, 

               Week(weekstart(TempDate)) & '-' & WeekYear(TempDate) as WeekYear, 

               WeekDay(TempDate) as WeekDay 

Resident TempCalendar 

Order By TempDate ASC; 

Drop Table TempCalendar; 

and here is the error:

The following error occurred:

Unexpected token: ')', expected one of: '(', ',', 'ZTestw_z', 'OPERATOR_PLUS', 'OPERATOR_MINUS', 'not', 'bitnot', ...

The error occurred here:

MasterCalendar: Load TempDate AS MYDATEFIELD, week(TempDate) As Week, Year(TempDate) As Year, Month(TempDate) As Month, Day(TempDate) As Day, YeartoDate(TempDate)*-1 as CurYTDFlag, YeartoDate(TempDate,-1)*-1 as LastYTDFlag, inyear(TempDate, Monthstart(>>>>>>)<<<<<<,-1) as RC12, date(monthstart(TempDate), 'MMM-YYYY') as MonthYear, ApplyMap('QuartersMap', month(TempDate), Null()) as Quarter, Week(weekstart(TempDate)) & '-' & WeekYear(TempDate) as WeekYear, WeekDay(TempDate) as WeekDay Resident TempCalendar Order By TempDate ASC

Your help is really appreciated!

7 Replies
petter
Partner - Champion III
Partner - Champion III

You should use RowNo() instead of IterNo() when you have an autogenerate.

http://help.qlik.com/en-US/qlikview/12.1/Subsystems/Client/Content/Scripting/CounterFunctions/IterNo...

IterNo() only works if you have a WHILE clause in your load staement.

Anonymous
Not applicable
Author

Thanks for your reply!

I changed it to RowNo(); however,  the same issue exists!

Any ideas?

Anonymous
Not applicable
Author

By the way, I am using Qlik Sense!

Gysbert_Wassenaar

Monthstart(>>>>>>)<<<<<<,-1

The variables don't get proper values. Try using numeric values instead of Date values:

Temp:

Load

               Num(min(MYDATEFIELD)) as minDate,  //Enter YourDateField from your data table

               Nume(max(MYDATEFIELD)+90) as maxDate  //Generate dates until 3 months from max date for regression

Resident MYTABLE;

Only in the master table apply the date format to TempDate get the correct MYDATEFIELD values. The While loop should work too when your variables have numeric values.


talk is cheap, supply exceeds demand
Anonymous
Not applicable
Author

Thanks for your reply!

I did; however the same error exists.

Here is the new Script

QuartersMap: 

MAPPING LOAD  

rowno() as Month, 

'Q' & Ceil (rowno()/3) as Quarter 

AUTOGENERATE (12); 

Temp: 

Load 

               (min(MYDATEFIELD)) as minDate,  //Enter YourDateField from your data table

               (max(MYDATEFIELD)+90) as maxDate  //Generate dates until 9 months from max date for regression

Resident MYTABLE

Let varMinDate = Num(Peek('minDate', 0, 'Temp')); 

Let varMaxDate = Num(Peek('maxDate', 0, 'Temp')); 

DROP Table Temp; 

 

TempCalendar: 

LOAD 

               $(varMinDate) + (RowNo()-1) As Num, 

               Date($(varMinDate) + RowNo() - 1) as TempDate 

               AutoGenerate 500;//1 While $(varMinDate) + RowNo() -1 <= $(varMaxDate); 

 

MasterCalendar: 

Load 

               TempDate AS MYDATEFIELD,  //This field is the key that connects to the data table

               week(TempDate) As Week, 

               Year(TempDate) As Year, 

               Month(TempDate) As Month, 

               Day(TempDate) As Day, 

               YeartoDate(TempDate)*-1 as CurYTDFlag, 

               YeartoDate(TempDate,-1)*-1 as LastYTDFlag, 

               inyear(TempDate, Monthstart(Date($(varMaxDate))),-1) as RC12, 

               date(monthstart(TempDate), 'MMM-YYYY') as MonthYear,  //This will be your dimension in the line-chart

               ApplyMap('QuartersMap', month(TempDate), Null()) as Quarter, 

               Week(weekstart(TempDate)) & '-' & WeekYear(TempDate) as WeekYear, 

               WeekDay(TempDate) as WeekDay 

Resident TempCalendar 

Order By TempDate ASC; 

Drop Table TempCalendar; 

here is the error:

TempCalendar << AUTOGENERATE(500) Lines fetched: 500

The following error occurred:

Unexpected token: ')', expected one of: ',', 'OPERATOR_PLUS', 'OPERATOR_MINUS', 'OPERATOR_MULTIPLICATION', 'OPERATOR_DIVISION', 'OPERATOR_STRING_CONCAT', 'like', ...

The error occurred here:

MasterCalendar: Load TempDate AS STG_FS_APPLICATIONSUPPORT.GCONTRACTDATE, week(TempDate) As Week, Year(TempDate) As Year, Month(TempDate) As Month, Day(TempDate) As Day, YeartoDate(TempDate)*-1 as CurYTDFlag, YeartoDate(TempDate,-1)*-1 as LastYTDFlag, inyear(TempDate, Monthstart(Date()>>>>>>)<<<<<<,-1) as RC12, date(monthstart(TempDate), 'MMM-YYYY') as MonthYear, ApplyMap('QuartersMap', month(TempDate), Null()) as Quarter, Week(weekstart(TempDate)) & '-' & WeekYear(TempDate) as WeekYear, WeekDay(TempDate) as WeekDay Resident TempCalendar Order By TempDate ASC

Gysbert_Wassenaar

Same error, same cause. Make sure your variable $(varMaxDate) gets a correct value. Can you post a small example qvw that demonstrates the issue?


talk is cheap, supply exceeds demand
shraddha_g
Partner - Master III
Partner - Master III

$(varMaxDate) is giving wrong value