Hi all,
I have a task scheduled based on multiple conditions. This setup has 1 trigger and 3 tasks which should have an AND relation between them.
- Signal A
- Signal B
- Daily signal
A and B are signals from our data warehouse to let us know when there is new data. These happen multiple times a day after 4 am.
The daily trigger was set on 4am.
The combination should allow us to start the task once a day when all of them are succesful. So A, B and daily need to be succesful together to initialize.
However, it already starts at 4am eventhough the other trigger happened after 4am.
Any idea why it did not wait until the last trigger?
Ok this might have something to do with the 'time constraint'. It had the default 360 min. This means the task to looked 6 hours back for any signals and this caused it to catch on the triggers from the previous day around 11pm.
Ok this might have something to do with the 'time constraint'. It had the default 360 min. This means the task to looked 6 hours back for any signals and this caused it to catch on the triggers from the previous day around 11pm.