Skip to main content
Announcements
Marching toward a simplified navigation! READ ON

Qlik Replicate Log Stream task error: End of time-line reached and all records were applied, task will stop

No ratings
cancel
Showing results for 
Search instead for 
Did you mean: 
OritA
Support
Support

Qlik Replicate Log Stream task error: End of time-line reached and all records were applied, task will stop

Last Update:

Mar 14, 2022 5:18:27 AM

Updated By:

Sonja_Bauernfeind

Created date:

Mar 11, 2022 11:07:04 AM

When a reload target is performed on the logstream staging task (parent) you will get the following error in every Log Stream remote task (child):

[SOURCE_CAPTURE ]W: End of timeline, no more records to read (ar_cdc_channel.c:1210)
[SORTER ]E: End of time-line reached and all records were applied, task will stop [1020101] (sorter_transaction.c:3486)

The task stops replication to the remote task.

 

Environment

 

Resolution

There are 2  optional ways to resolve this issue:

Option 1:  Reload the Log Stream remote (child) task

Option 2: Start the Log Stream stagging task (parent) from the timestamp before its reload. To do this please follow the steoos below: 

  1. Find the log of the log stream  staging  task(parent) just  before the reload was performed. i.e. reptask_TASKNAMEof_STAGING_TASK?????.log. that has a date just before the reload was performed.
  2. Go to the end of the log in step one and get the line that says Final saved task state. At the end of the line get the timestamp
  3. Once you get the timestamp, you will need to convert the EPOCH time to Server Time
  4. Use that time to start the task.

 