Hi Experts,
I need to trigger a task on completion of multiple other tasks. I have tried the trigger "On multiple events completed", but somehow it doesn't work. The dependent task never starts.
Can anyone please help me to find what's going wrong here?
Thanks,
Bhalchandra
But other tasks that you called Job1 and Job2 have been scheduled?
Yes. They are scheduled to trigger on same common event.
So they are scheduled depending on other tasks?
Yes.
Which version of QV are you running?
Version 11
Ok But these other task are scheduled that is
MAIN TASK depends on Job1, Job2 Both scheduled
Job1 depends on Job11 (Scheduled)?
Job2 depends on Job22 (Scheduled)?
I think that at the end of this chain something doesn't work
Which SR?
Like 11 sr2 or 11.2 Sr1?
There was a problem with multiple events in one SR release on 11.2
Hi Alessandro,
The chain is something like this:
MAIN TASK depends on Job1, Job2 Both scheduled
Job1 depends on Job11 On EDX
Job2 depends on Job22 On EDX
Hi Jerry,
Its 11 SR2