Hi there,
I have a Qlikview overview that shows for each invoice the order date and the delivery date.
Substracting both dates gives me the lead time between order and delivery.
However, the result of this formula is influenced negatively by weekend days.
Does someone know if it possible to calculate only working days between two dates within Qlikview. In excel it is feasible but it would be great if I could get this information within the Qlikview table of course.
Thanks for your feedback or ideas.
Peter
Hi Peter,
You can use Networkdays() function.
Go through this link
Hi,
Did you give networkdays() a try?
Thanks,
RT
Try to share that excel file which working so then we may replicate that in View.
In your master calendar, could you identify which days are work days, and which weekend?
Load this as a new dimension and use in the set analysis
Hi,
Networkdays will resolve the issue. Passing Order date as Start date and Delivery date as end date will give you the working days.
Hope it helps.
Thanks