Skip to main content
Announcements
Join us at Qlik Connect for 3 magical days of learning, networking,and inspiration! REGISTER TODAY and save!
cancel
Showing results for 
Search instead for 
Did you mean: 
Not applicable

How do I calculate the sum of a field depending on the most recent date?

Hi all,

So I am trying to make a bar chart that will show me the total cost by Project Sponsor. The problem is that I want it to only calculate depending on the latest date for that project flash report.

Project NumberNameDateProject Sponsor
1Test 101/02/2014Ben
2Test 201/02/2014Luke
3Test 301/02/2014Luke
4Test 402/02/2014Adam

Project NumberDateCost
103/03/2014100
105/04/2014200
201/03/2014400
209/04/2014150
202/05/2014340
314/03/2014600
320/04/2014700
401/03/2014230
408/04/2014

250

I have something like the above. The two tables are linked by the Project Number. So if I calculate the sum of Cost only with the max date, the results I would expect are: Ben would have a total of 200. Luke would have a total of 1040. And Adam would have a total of 250.

So to make it clear, each person will have a number of projects and the cost changes every month depending on what they spend. So i want to get the total cost for each person. The person being the dimention.

Many thanks,

Bruno

1 Solution

Accepted Solutions
maxgro
MVP
MVP

try with

sum(

     aggr(FirstSortedValue(total <[Project Sponsor], [Project Number]> Cost, -Date),

          [Project Sponsor], [Project Number])

)

View solution in original post

4 Replies
Not applicable
Author

Attached with answer.

Thanks

AJ

maxgro
MVP
MVP

try with

sum(

     aggr(FirstSortedValue(total <[Project Sponsor], [Project Number]> Cost, -Date),

          [Project Sponsor], [Project Number])

)

Not applicable
Author

Your script should be

Load * inline
[
Project Number, Name, Date, Project Sponsor
1, Test 1, 01/02/2014, Ben
2, Test 2, 01/02/2014, Luke
3, Test 3, 01/02/2014, Luke
4, Test 4, 02/02/2014, Adam
]
;

Load * inline
[
Project Number, Date1, Cost
1, 03/03/2014, 100
1, 05/04/2014, 200
2, 01/03/2014, 400
2, 09/04/2014, 150
2, 02/05/2014, 340
3, 14/03/2014, 600
3, 20/04/2014, 700
4, 01/03/2014, 230
4, 08/04/2014, 250
]
;

in Dimension use Project Sponsor

and in Expression use

=sum(aggr(FirstSortedValue(total <[Project Sponsor], [Project Number]> Cost, -Date1), [Project Sponsor], [Project Number]))

you will get

Maxdatesum.PNG.png


Vinay

Not applicable
Author

Thanks guys,

They all work.

=sum(aggr(FirstSortedValue(total <[Project Sponsor], [Project Number]> Cost, -Date1), [Project Sponsor], [Project Number]))

The one above is the one I was looking for, thank you

Kind regards,

Bruno Pereira