Hi,
I am trying to figure out how to add 2 months to an expression but only show the current dates in the dimensions. For example, for June, I need to show data in August because of a 60 day grace period. Can someone show me how I can do this without showing August in the dimensions for June.
Please let me know if you need further clarification to answer this question.
Thank you,
Saurav
Hi Saurav S
Can you try Addmonths(today(),2), which gives you your expecting result.
hope this helps
thank you
Meher
Hi Merwan,
Sorry I forgot to mention. I have already done addmonths in my script but in the dimensions I do not need to see July and August in June. I believe showing the future months will confuse the end users. Do you think there is a solution?
Hi
This is what I would try:
DateIsland:
LOAD
TransDate As diDate,
AddMonths(TransDate, 2) As diGraceDate
Resident Data;
Sum(If(TranDate < diGraceDate, Value))
or
Sum(If(Month(TranDate) = Month(diGraceDate), Value))
Hope that helps