I need to setup a job which is depending on successor of a daily run, but I want my job only to be run on Friday? Is there any way to schedule that on QMC
Create a blank qvw (lets call it FridayTrigger.qvw), and create a task for this to run only on a Friday. Then for your job, create an "on Multiple Events Completed" trigger that will check to see completion of the daily task run and the FridayTrigger task run. Adjust the time constraint* as required.
* this is the maximum time interval between the completion of the tasks. they must complete within this interval to satisfy the trigger
You will want to put DailyTrigger.qvw in a folder that is not mounted on the access point.
Hi Eromiya,
May be you need write code in qvw like below:
If(Weekday='FRI*')
.
.
All Code
..
..
else
.
.
Exit;
Thanks,
Arvind Patil