I'm working on a Grid chart with the X dimension being a "Implementation Date". The Implementation Date can be any date in 2017. Is there a way to write an expression that draws reference lines to at the start or end of each quarter?
Hmm Strange it is not working as expected. Can you try like giving the S_Improv...Date in Reference line hardcoded for Q1.
Some reference here: Check it:
Not quite sure I understand what you mean
I feel like I'm getting close. I'm currently working on this expression. I would have expected it to draw a line at the end of March, but it drew it and the first date on the chart
If(inquarter([S_Improvement Implemented Date], '30-Mar-2017', 0)='1',-1,0)
Something like this?
This is amazing. Thanks sunny for looking into this. Learnt something new. 🙂
Sunny, that is perfect. Thanks for your Help! I can't seem to find the option to mark this as correct in the discussion. I did mark it as Helpful though!
It is exactly what I need!