Good day,
I have a schedule that reloads my document daily. My question is how do you specify that this document reloads twice on one specific day.
Thank you
Kamiel
Hello Kamiel,
If you are running QlikView Server, set two hourly reload tasks (one each 12 hours) instead one daily. If you are using the Windows Scheduler you can do the same.
Hope that helps.
Miguel
Thank you Miguel,
I only want this to happen on a Sunday and the rest of the loads will be once a day.
Hi,
Still don't know whether or not you are running a QlikView Server. Anyway, then create two different tasks instead: one for Sundays only that will load twice, another weekly for Monday to Saturday once.
Hope that helps.
Miguel