Hi Experts !
I wondered if you could give me some help on a small app I am trying to create to build a very simple schedule table. I have a list of tasks with a start and finish dates fields. I manage to create all the dates in between those start and finish dates, so I can represent these easily , as can be seen in attached qvw file. The problem is I would need to skip all weekends ( and optionally holiday dates ), so the duration of these tasks should account for only working days. I am not sure how I would need to enter the holiday dates , maybe an INLINE table ...but how ? . Also I would need to see days in between two tasks even if there is no work done on these dates.
Current qvw app chart :
Expected chart ( what I would need ) , based on an excel mockup :
I would appreciate any guidance you could give me here.
Many thanks in advance
Enrique
Hi Enrique,
View this links
Master Calendar with movable holidays
How to remove weekend and holidays from your calculation
Regards,
Andrey
Thanks Andrey for providing these links, there are tons of good information there.
I already read a god post by legend Henric Cronström, where I learnt how to create all reference dates for my dates intervals ( date_start and date_finish )
Creating Reference Dates for Intervals
I wondered if there would be a simple script modification to that one already in my app, that could provide all the reference dates between my start and finish dates BUT excluding the weekends ( and optionally holidays ).
I could probably join that table to a master calendar to get my expected result ( as in my excel mockup printscreen )
FillDates:
LOAD
key,
networkdays(date_start, date_finish) as Work_days,
Date(date_start + IterNo()-1) as date_Fill
RESIDENT Tasks
While IterNo()<= date_finish - date_start + 1;
Thanks again for your time and help