Hi All,
I have the following Doughnut Chart that shows cases picked versus total.
What I want to do next is to show the potential finish time based on Current Average and Potential finish time if I add more people to a task.
I have the following variables
input.volume.picking = 20,000
input.picking.ops = 0
I have the following Expression to look at what has been picked so far today, which is then divided by the $(input.volume.picking) to get % complete
So I want to get average cases picked per hour and then what that average would be if I added more pickers. Just wondering where to start with this?
Maybe something like this? but i need a new End Time
Amount / Start Time - End Time /Current Ops* $(input.picking.ops)
Struggling!!
Alan
The variable input.volume.picking was set to value 50000 instead of 20000.
EndTime is a date. If you add 1 to it you get the next day. If you add 4.06 to it you get a datetime that's 4 days and a bit later. So you need to divide the 4.06 by 24 first since 4.06 is supposed to be a number of hours, not days. Finally you want the end result formatted as a time, not just the EndTime. Try this instead:
=TIME(($(input.volume.picking)
-
SUM({<Date = {"$(=MAX(Date))"},[Trx Type] ={'D'},ActionId ={'PICKCASE'}>}Primary))
/
NUM((SUM({<Date = {"$(=MAX(Date))"},[Trx Type] ={'D'},ActionId ={'PICKCASE'}>}Primary)
/SUM({<Date = {"$(=MAX(Date))"},ActionId ={'PICKCASE'},[Trx Type] = {'D'}>}NewPickTime)),'#,##0')/24
+
MAX({$<Date = {"$(=MAX(Date))"},[Trx Type] = {'D'},ActionId = {'PICKCASE'}>}EndTime))
Little understand from your question.
Could you provide at least one example with result so that we can help you by understanding your logic more clearly.
Hi
To calculate a potential completion time, you need the following:
Then:
And
HTH
Jonathan
Here is what I have
Obvoiusly I have expressions behind all of these and they are correct.
Right now I can deal with getting average times
So it would be
Cases Due - Cases Picked = 7,108/Average Cases per Hour = 1750
The result is 4.06, Can I just add this to the Max PickTime of 09:30:50?
Here is the Expression I have to do this, but the result is not correct
I am hoping to for a Finish Time of 13:30
However the result being returned is 61683.028078705
Hi All,
I have attached a reduced version of the file
Any ideas with this?
Hi Manish,
Any chance you could take a look at this?
Apologies for being annoying, just trying to get this sorted before the weekend
Thanks
Alan
The variable input.volume.picking was set to value 50000 instead of 20000.
EndTime is a date. If you add 1 to it you get the next day. If you add 4.06 to it you get a datetime that's 4 days and a bit later. So you need to divide the 4.06 by 24 first since 4.06 is supposed to be a number of hours, not days. Finally you want the end result formatted as a time, not just the EndTime. Try this instead:
=TIME(($(input.volume.picking)
-
SUM({<Date = {"$(=MAX(Date))"},[Trx Type] ={'D'},ActionId ={'PICKCASE'}>}Primary))
/
NUM((SUM({<Date = {"$(=MAX(Date))"},[Trx Type] ={'D'},ActionId ={'PICKCASE'}>}Primary)
/SUM({<Date = {"$(=MAX(Date))"},ActionId ={'PICKCASE'},[Trx Type] = {'D'}>}NewPickTime)),'#,##0')/24
+
MAX({$<Date = {"$(=MAX(Date))"},[Trx Type] = {'D'},ActionId = {'PICKCASE'}>}EndTime))
Excellent, this works
I was not far away, I did not format the time and I was not dividing by 24 to get the hours
How long are you using Qlikview? you have all the answers
Thanks so much Gysbert
Kind Regards
Alan
Hi Gysbert,
One final question, I swear.
If I want the End Time to change based on the number of guys I add to a task, for example if I have 4 current pickers and change to 5 using the $(input.picking.ops).
My question is how do I get the current Pickers, would it be something like if they have picked in the last 2 minutes to get the current pickers?
Not sure how to get this.
Time functions cause me problems for some reason!!
Thanks again