calculation of openning qty from closing qty for next day?

Hi All

I am having a table which has details of material, their closing quantity and date.

so daily this closing quantity is moving and I want to store their closing quantity as a opening quantity for next day.

Can anybody provide any logic/approach.

I have attached the sample data where input table is a having material, quantity and Date,

Pls check output table where I have to show opening quantity from previous closing quantity.

Thanks In advance

6 Replies
tresesco
MVP
MVP

Do you need them material wise?

MayilVahanan

Hi

Try like this

Test:

LOAD * INLINE [

    Date, Material, ClosingQTY

    8/10/2013, X1, 10

    8/10/2013, X2, 8

    8/10/2013, X3, 12

    9/10/2013, X1, 8

    9/10/2013, X2, 10

    9/10/2013, X3, 15

    10/10/2013, X3, 9

    10/10/2013, X1, 4

    10/10/2013, X2, 4

];

Load

  Date, Material, If(Material <> Previous(Material),' ', Previous(ClosingQTY)) As OpeningQty, ClosingQTY

Resident Test

Order By Material,Date;

DROP Table Test;

Hope tat helps

Thanks & Regards, Mayil Vahanan R
Please close the thread by marking correct answer & give likes if you like the post.
Not applicable
Author

Material and datewise

tresesco
MVP
MVP

Please see the attached sample.

Not applicable
Author

Thanks  Tresesco

Not applicable
Author

HI Tresesco

I have implemented it, and it is working fine but a problem arises when there is more material in previous day and less material on current day.

I have attached the sample QVW.

Pls check for closing QTY for date 09-10 which  is 47. This Closing QTY value suppose to be the opening QTY for next day but because of less nos of material on next day i.e.(date 10-10)  it rejects one record whose material is X4. This material is available on date 09-10 but not available on date 10-10-2013. I think this is the reason it is not calculating it.

Pls suggest how to calculate so that it gives correct opening QTY or any new logic?.