convert to time format

I have calculated the interval between all the times I have in emptyings_time;

emptyings_time is a time field.

The interval has small values, mostly a minute or 2.

This is my interval calculation:

=below(emptyings_time,1)-(emptyings_time)

In the pivot I selected time as format and that works perfectly, but now I want to use it in a chart.

Where I can't select the time format, so I have to change it another way.

Can anyone please help?

9 Replies
Not applicable
Author

can you attach sample file?

ashfaq_haseeb
Champion III
Champion III

Hi,

look at the attached document

Regards

ASHFAQ

Not applicable
Author

The interval is always 00:00:00 that isn't correct.

It should be 1 minute (most of the intervals)

Not applicable
Author

I attached a qvw file with sample data.

Good luck!

Not applicable
Author

actually it will not work like this way, you need to add the interval on pre load, while reading the data you need to calculate this interval.

I will try to make it today for you. once I finish my work.

good luck.

Not applicable
Author

That would be great, thank you!

I'm still pretty new to qlikview, so I look forward to see how it is done correctly

ashfaq_haseeb
Champion III
Champion III

Hi,

Look at the attached document.

Regards

ASHFAQ

Not applicable
Author

This is it.... ashfaq_haseeb  you did it.

Not applicable
Author

Looks great!

How do I get these time intervals in a graph?

With on the horizontal axes the hours of a day

on the vertical axes the intervals, and as expression also the intervals.