Execute a Job after Multiple Jobs are complete.

Hi,

I have a requirement to execute one talend job after 3 talend jobs are complete, these 3 talend jobs would run in parallel and once all three are complete i would need to trigger the 4th job.
I know i have to use Run Job to achieve this but would like to know the dependencies to be set between each of them.
Thanks & Regards,
Srivignesh KN

Labels (2)
1 Reply
Anonymous
Not applicable

Hi 
tParallelize component allows you to parallelize and synchronize the subjobs in the same job, however, this component is only available in Talend Enterprise subscription product. With open studio, you can achieve it with tRunJob component. 