Hi,
I have a parent job wherein there are two child jobs
P1 -> C1,C2
I am executing these P1 job using multi thread execution
Now i have three more child jobs in C1
C1 -> CC1,CC2,CC3
I want to run these child jobs in parallel
Can i also apply multi thread to C1 also and run the talend job ?
So final execution is two multi thread exécutions in one talend job, will it work or will it create some sort of problem.
Note : The process in the jobs is all separate, there is no dependency of the data between the jobs.
Thanks
Hi vidya,
Personally, when I want to parallelize some component or subjob, I use a "tExecutors" component. You can find it on talend exchange.
It's pretty good and easy to use.
Good luck !