Hi ,
Recently moved to talend 6.0.1 from 5.6.2. Multithread execution is not working as it should be.
The scenario is like this
I have a main job which will call two sub jobs in a tinfinite loop with intervals (this serves as a daemon job for us). This calls two subjobs. The subjobs are executed as a independent process. The interval is set to 5 min(in milliseconds) for both the job. The subjobs finishes under a minute.
The first execution of the main job is ok where both the subjobs are called in parallel. But from the next loop onwards the threads are called serially. This worked in 5.6.2 but not in 6.0.1
Bit stumped here.... any help appreciated.
Regards
Jay