I?ve a job which queries a lot of different slow databases and creates a summary report at the end. From the optimization perspective it would make sense to parallelize some of the queries.
Which options provides TOS to parallelize jobs or components?
I?ve seen the ?Multi thread execution? in Job Settings. But to my understanding has this option only an effect on lookup loading. The documentation is a little bit light on parallel computation. The only reference I found was in ?Defining the Start component? and from the comments there it does not look like that I can parallelize the waiting time for the databases.
I?m not sure if it would work if I encapsulate the different queries in unlinked sub jobs. The biggest issue I would see with this approach is the synchronisation before the data consolidation because I have to wait until the last job finishes. In addition I?m not sure the system really starts the unlinked jobs in parallel. Did someone already test something like that?
Labels (2)
14 Replies
Anonymous
Not applicable
Author

Here is what we can currently do, in TOS 2.3.x, in Java project only. "Multi threading" option must be enabled in the preferences.
In the child job (with 2 unlinked subjobs), ths 2 subjobs are executed in parallel. The problem is that we can't execute a third subjob that would wait for the others to have finished (this will be added in TOS 2.4). The workaround is to use a tRunJob to "wait for" the 2 subjobs (in the child job).
Anonymous
Not applicable
Author

Thx for your response, your answer helps.
I need to try few things out to see if there are any pitfalls. The different queries have huge differences in execution time and some queries provide input for others so I may need more then one level to implement the queries. If I have sub jobs in sub jobs will it still work?
Anonymous
Not applicable
Author

If I have sub jobs in sub jobs will it still work?

What do you mean? (I know the "Talend Open Studio" glossary is missing, it is being prepared) Do you mean you have iterate links?
Anonymous
Not applicable
Author

I?m currently implementing it as iterative link, yes.
One tOracleInput is iteratively linking to one or more other tOracleInput components.
I?m not sure it?s the best way to deal with it. The job goal is to validate data consistency between different databases and the current implementation follows my workflow when I do it by hand.
PS: I?m not sure the picture is really readable but may give you a rough overview. There are databases missing so it?s not the full picture anyway.
_AnonymousUser
Specialist III
Specialist III

Hello plegall,
on 2008-03-07 you wrote "The problem is that we can't execute a third subjob that would wait for the others to have finished (this will be added in TOS 2.4)". Is the option to directly re-syncrhonize subjobs evailable meanwhile?
thanks for your answer
Peter
Usman1
Contributor
Contributor

Hi,
I am currently using Talend 2.4.1. I have the same problem. I have 3 runjobs which should run in parallel and when they are finished they should execute a set of processes only once. In the uploaded image, I have replaced the whole set of processes by only one stored procedure call for simplicity purposes.
By the way, just by curiosity, if I have one task that depends on the success of at least one of N tasks, how can I model this on Talend.
Thanks for your help!!
Usman
Anonymous
Not applicable
Author

on 2008-03-07 you wrote "The problem is that we can't execute a third subjob that would wait for the others to have finished (this will be added in TOS 2.4)". Is the option to directly re-syncrhonize subjobs evailable meanwhile?

This feature has been added to Talend Integration Suite (and not to Talend Open Studio as I thought at the very beginning). See the screenshot to have an example of what can be done.
Anonymous
Not applicable
Author

I am currently using Talend 2.4.1. I have the same problem. I have 3 runjobs which should run in parallel and when they are finished they should execute a set of processes only once. In the uploaded image, I have replaced the whole set of processes by only one stored procedure call for simplicity purposes.
By the way, just by curiosity, if I have one task that depends on the success of at least one of N tasks, how can I model this on Talend.

With Talend Integration Suite (see my screenshot in my previous post), you can configure the tParallelize to "wait for end of first subjob" or "wait for end of all subjobs".
Anonymous
Not applicable
Author