Please I need help calculating time. I need to create a report which shows active time to complete a project. The metrics is in hours and I would like to convert to days. Do I divide by 8 or 24?

1 Solution

Accepted Solutions
dplr-rn
Partner - Master III
Partner - Master III

Depends on how the metric is defined by business. I would hazard a guess they want Man Days and so divide by 8

View solution in original post

2 Replies
dplr-rn
Partner - Master III
Partner - Master III

Depends on how the metric is defined by business. I would hazard a guess they want Man Days and so divide by 8
Pomna
Creator III
Creator III
Author

Thank You Dilipranjith