Qlik Reload Scheduled Task not starting on time

Hey,

I have a reload task with two triggers, for 6am and 6pm. The 6pm works as expected.

The 6am trigger is constantly delayed by about 20 minutes.

The log file doesn't indicate anything wrong, and the first entry is the trigger firing. 

What could be the cause of this delay?

 

Labels (1)
1 Solution

Accepted Solutions
Vegar
MVP
MVP

do you have other jobs running around 6am? It could be that the server is to busy to run the task st that moment.

 

in those  cases you should see that the task is status  "triggered".

 

Read more on tasks here: https://help.qlik.com/en-US/sense-admin/November2022/Subsystems/DeployAdministerQSE/Content/Sense_De...

View solution in original post

1 Reply
Vegar
MVP
MVP

do you have other jobs running around 6am? It could be that the server is to busy to run the task st that moment.

 

in those  cases you should see that the task is status  "triggered".

 

Read more on tasks here: https://help.qlik.com/en-US/sense-admin/November2022/Subsystems/DeployAdministerQSE/Content/Sense_De...