Scheduling multiple tasks at one main master task in Qliksense QMC

Hi All ,

Please kindly assist me in scheduling a Master Task Say - 

RecordSourceQVDTasks that will have three Tasks.

1.RecordSource - after complettion of this tasks task 2 will start

2.RecordInsurer - after complettion of this tasks task 2 will start

3.RecordSourceInsurerMap - End.

It would be helpful if anyone can show the steps in details. 

 

Many Thanks,

Suvechha

 

List.PNG

1 Solution

Accepted Solutions
suvechha_b
Creator III
Creator III
Author

First Create Task -

1.RecordSource

Secondly , Create  Task

2.RecordInsurer where the trigger needs to be created and point it out to Task Record Source.

Task11.PNG

 

3. Create Task 

RecordSourceInsurerMap - and the trigger needs to point RecordInsurer Task.

Now, You can set an schedule trigger and set time on the first task .

I was confused about the creation of trigger. I was creating the trigger on the first task.

 

View solution in original post

5 Replies
suvechha_b
Creator III
Creator III
Author

Hi ,

I have create a task chain , but how can I change from Preceding task to following task.

change.PNG

anderseriksson
Partner - Specialist
Partner - Specialist

?

Your questions does not make much sense?
Try to explain better what it is you want to achieve.
Task chaining is no mystery, you just select the trigger to be on 'Task event trigger'.
This is in the trigger of the following task.

suvechha_b
Creator III
Creator III
Author

First Create Task -

1.RecordSource

Secondly , Create  Task

2.RecordInsurer where the trigger needs to be created and point it out to Task Record Source.

Task11.PNG

 

3. Create Task 

RecordSourceInsurerMap - and the trigger needs to point RecordInsurer Task.

Now, You can set an schedule trigger and set time on the first task .

I was confused about the creation of trigger. I was creating the trigger on the first task.

 

anderseriksson
Partner - Specialist
Partner - Specialist

The Task Chain in QMC shows what the selected task is triggered by.
You specify what the current task is triggered by, NOT what following tasks should be triggered by the current task.
Don't now of any convenient way of seeing what is triggered by a specific task.