I need to schedule a reload task with the following requirements:
To Summarize this, reloads for the app should be every 3 hrs. But these reloads should happen between 3pm current day and 6am next day. Pls note, the avg time to reload this app is 1 hr.
thanks in advance.
@sunny_talwar @Sonja_Bauernfeind
Hi,
Maybe something like that ?
Reference doc: Tasks - Custom option | Qlik Sense for administrators Help
Best
thanks dear, Could you please suggest if we can add these 2 conditions in the same reload task ? Currently we have a chain task.
In the meantime I have created schedules based on the suggestion. can see next execution time is based on the expectation. will monitor the last reload for these 2 schedules and confirm back.