		Hi Experts,
I want schedule the Auto refresh in qlik sense.
Previously i did it in qlik view with this statement in edit script
EXECUTE "C:\Program Files\QlikView\QV.exe" /r "D:\Qlikview\auto refresh.qvw";
Same thing I trying in qlik sense also but i am not able find this path''C:\Program Files\QlikView\QV.exe'' which i wrote for qlik view
I am taking the data from sql server database and i have created qvd's then i performed joins operation. Now total i have 4qvd's but our client will not open those 4 qvd's he will open final front end qvd only. so whenever he load the data in front end qvd automatically it will refresh backend qvd's also
Is there any option is there for that
Can you guys help me out from ..
Thank you in advance
B VS Sudhakar
 
					
				
		
 jonathandienst
		
			jonathandienst
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Unfortunately, the QV way does not work out of the box for Sense. There are a range of extensions in Qlik Branch that allow reloading the desktop, including reloading from a batch or script file.
 bvssudhakar
		
			bvssudhakar
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Hi Jonathan
can you please elaborate how to do this
 bvssudhakar
		
			bvssudhakar
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Scheduling Auto refresh in qliksense
Can you guys Please help me out from this
Rob Wunderlich mbaeyensmtotrdandamudistalwar1maxgroswuehllfhollandmanoj217kkkumar82trdandamudiloveisfail
 priyalvp24
		
			priyalvp24
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Hi,
Steps are as follows
1)Open QMC
2)Go to Tasks
3)Click On Create new
4)Enter the Task Name
5)Select the Dashboard Application Name
6)Click On Action
7)Select the refresh frequency.
Thanks....
 priyalvp24
		
			priyalvp24
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Hi,
Steps are as follows
1)Open QMC
2)Go to Tasks
3)Click On Create new
4)Enter the Task Name
5)Select the Dashboard Application Name
6)Click On Action
7)Select the refresh frequency and click on Apply. So reload will happen as per frequency on front as well as back end
Thanks....
.png) 
					
				
		
 Miguel_Angel_Ba
		
			Miguel_Angel_BaYou need Qlik Sense Enterprise to schedule loads. There is no equivalent to qv.exe /r in Qlik Sense.
 bvssudhakar
		
			bvssudhakar
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Hi Miguel,
I am using Qlik sense desktop version. Is there any Possibility for this Edition
 bvssudhakar
		
			bvssudhakar
		
		
		
		
		
		
		
		
	
			
		
		
			
					
		Hi Priyal,
I am using Qlik sense desktop version. Is there any Possibility for this Edition
.png) 
					
				
		
 Miguel_Angel_Ba
		
			Miguel_Angel_BaAs I mentioned, this is not possible with Qlik Sense Desktop.