Do not input private or sensitive data. View Qlik Privacy & Cookie Policy.
Skip to main content

Announcements
ALERT: QlikView server communication interruptions following Microsoft Windows Domain Controller security updates
cancel
Showing results for 
Search instead for 
Did you mean: 
buzzy996
Master II
Master II

partial sum not appering properly

hi,

the expected out put for first row  is around 160 hours.

any help?

thx

Labels (1)
1 Solution

Accepted Solutions
veidlburkhard
Creator III
Creator III

Hi Shive,

that's easily solved: you did use 'Time' as your number format, but Time adds to max 24 h. You should use 'Interval' instead:

Interval.jpg

View solution in original post

2 Replies
veidlburkhard
Creator III
Creator III

Hi Shive,

that's easily solved: you did use 'Time' as your number format, but Time adds to max 24 h. You should use 'Interval' instead:

Interval.jpg

buzzy996
Master II
Master II
Author

ya,couldn't get that thought earlier,thanks.