Enclosed I have report with contracts of our organisation. We have an start- and enddate plus annual amounts.
I got the following question:
example startdate September 1st 2014 - Enddate August 31st 2015
yearly amount EUR 12.000 (not divided in months).
for 2014 I want to see EUR 4.000 costs (Sept - Dec) to expect and for 2015 I want to see that I can expect EUR 8.000 costs (Jan - Aug).
Is that possible?
ope to hear from anyone.
Regards,
Kees-Jan