hi,

the expected out put for first row  is around 160 hours.

any help?

thx

1 Solution

Accepted Solutions
veidlburkhard
Creator III
Creator III

Hi Shive,

that's easily solved: you did use 'Time' as your number format, but Time adds to max 24 h. You should use 'Interval' instead:

Interval.jpg

View solution in original post

2 Replies
veidlburkhard
Creator III
Creator III

Hi Shive,

that's easily solved: you did use 'Time' as your number format, but Time adds to max 24 h. You should use 'Interval' instead:

Interval.jpg

buzzy996
Master II
Master II
Author

ya,couldn't get that thought earlier,thanks.